dátum |
plánovaný
|
odhad NDS
|
- predĺženie
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||
243,5 km |
2 - 6 |
2 642 mil. € |
-0,3 km |
4,8 |
4,6 |
|||||||
1 | 8. - 9. | 3/2024 | ![]() | 6,2 km | 2 | 105 mil. € | 0,0 km | 1 416 | 2 | 2 | ||
2 | 37. - 38. | 2/2028 | ![]() | 7,8 km | 2 | 73 mil. € | -0,5 km | 1 199 | 5 | 4 | ||
3 | 44. - 45. | 2/2029 | ![]() | 18,0 km | 2 | 176 mil. € | 0,2 km | 1 146 - 1 203 | 5 | 5 | ||
4 | 44. - 45. | 2/2029 | ![]() | 3,6 km | 4 | 133 mil. € | 5 | 5 | ||||
5 | 47. | 7/2029 | ![]() | 14,0 km | 2 | 117 mil. € | 0,0 km | 1 335 - 1 725 | 5 | 4 | ||
6 | 62. - 63. | 10/2032 | ![]() | 8,5 km | 6 | 90 mil. € | 9 787 | 5 | 5 | |||
7 | 62. - 63. | 10/2032 | ![]() | 6,9 km | 6 | 107 mil. € | 5 | 5 | ||||
8 | 71. - 78. | po 2040 | ![]() | 42,1 km | 4 | 631 mil. € | 1 113 - 2 310 | 5 | 5 | |||
9 | 71. - 78. | po 2040 | ![]() | 29,2 km | 2 | 230 mil. € | 607 - 1 070 | 5 | 5 | |||
10 | 71. - 78. | po 2040 | ![]() | 3,1 km | 4 | 60 mil. € | 1 014 - 1 369 | 5 | 5 | |||
11 | 71. - 78. | po 2040 | ![]() | 32,8 km | 2 | 367 mil. € | 328 - 768 | 5 | 5 | |||
12 | 71. - 78. | po 2040 | ![]() | 71,3 km | 2 | 553 mil. € | 215 - 1 012 | 5 | 5 | |||
243,5 km |
2 - 6 |
2 642 mil. € |
-0,3 km |
4,8 |
4,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku