dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 53. - 54. | 7/2030 | 11,3 km | 2 | 3 310 m | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2030 | ||||
2 | 57. - 58. | 6/2031 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 6/2031 | |||||
3 | 62. - 63. | 10/2032 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2032 | ||||
4 | 62. - 63. | 10/2032 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2032 | ||||||
5 | 69. - 70. | 8/2034 | 14,0 km | 2 | 2 641 m | 305 mil. € | 3 | 3 | 8/2034 | |||||
6 | 69. - 70. | 8/2034 | 49,0 km | 2 | 2 587 m | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2034 | ||||
7 | 71. - 78. | po 2040 | 1,7 km | 2 | 944 m | 54 mil. € | 7 972 | 3 | 4 | po 2040 | ||||
146,2 km |
2 - 6 |
9 482 m |
2 460 mil. € |
2 561 - 32 968 | 3,9 |
4,1 |
7/2030 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku