dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 272 mil. € | 5 792 - 7 064 | 3 | 2 | 3,0 | 7/2023 | 12/2029 (+5,4) | |||||
2 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 5,0 | 5/2024 | 10/2028 (+3,2) | |||||
3 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 9,0 | 6/2029 | 5/2033 (+10,2) | |||||
4 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 32 968 | . . . | 5 | 5 | 9,0 | 1/2031 | 10/2035 (+5,6) | ||||
5 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 9,0 | 1/2031 | 10/2035 (+5,9) | ||||||
5 úsekov |
55,0 km |
2 - 6 |
1 085 mil. € |
5 792 - 32 968 | 3,8 |
3,6 |
10/2028 - 10/2035 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku