dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | R 24,5/120 | 191 mil. € | 6 428 - 9 084 | 4 | 5 | 7/2023 | 9/2028 (+3,5) | |||||
2 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 5/2024 | 10/2028 (+3,2) | |||||
3 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | R 11,5/80 (60) | 94 mil. € | 7 211 | 4 | 2 | 1/2030 | 8/2034 (+2,1) | |||||
4 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | D 33,5/120 | 90 mil. € | 32 968 | . . . | 5 | 5 | 1/2031 | 10/2035 (+5,6) | ||||
5 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | D 33,5/120 | 107 mil. € | 5 | 5 | 1/2031 | 10/2035 (+5,9) | ||||||
5 úsekov |
49,5 km |
2 - 6 |
759 mil. € |
6 428 - 32 968 | 4,0 |
3,8 |
9/2028 - 10/2035 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku