dátum |
plánovaný
|
odhad NDS
|
pozemky
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||
1 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 10,0 mil. € | 7 234 | 4 | 3 | 7/2033 (+4,3) | ||||
2 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 11,0 mil. € | 2 561 - 5 054 | 4 | 3 | 7/2033 (+4,3) | ||||
3 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 12,0 mil. € | 7 211 | 4 | 2 | 8/2034 (+2,1) | ||||
4 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 6,0 mil. € | 5 586 - 10 745 | 3 | 2 | 8/2034 (+2,1) | ||||
5 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 4,4 mil. € | 32 968 | . . . | 5 | 5 | 10/2035 (+5,6) | |||
6 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 3,9 mil. € | 5 | 5 | 10/2035 (+5,9) | |||||
7 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 15,0 mil. € | 3 | 3 | 8/2037 (+5,9) | |||||
8 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 60,0 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||
9 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 92 mil. € | 15,0 mil. € | 5 098 - 5 557 | 4 | 2 | po 2040 (0,0) | ||||
130,7 km |
2 - 6 |
1 882 mil. € |
137,4 mil. € |
2 561 - 32 968 | 4,0 |
3,2 |
7/2033 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku