dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | po Lučenec 9 371, ďalej 8 954 | 6 969 - 10 726 | 4 | 4 | 11/2023 | 4/2028 (+4,8) | ||||
2 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 5 938 - 12 956 | 7 234 | 4 | 3 | 2/2028 | 7/2033 (+4,3) | ||||
3 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 1 942 - 3 996 | 2 561 - 5 054 | 4 | 3 | 2/2028 | 7/2033 (+4,3) | ||||
4 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 41 057 | 32 968 | . . . | 5 | 5 | 1/2030 | 10/2035 (+5,6) | |||
5 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 46 864 | 5 | 5 | 1/2030 | 10/2035 (+5,9) | |||||
6 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 10 765 | 3 | 3 | 2/2032 | 8/2037 (+5,9) | |||||
6 úsekov |
72,6 km |
2 - 6 |
1 117 mil. € |
2 561 - 32 968 | 4,2 |
3,8 |
4/2028 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku