dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | po R. Sobotu 7 978, ďalej 8 783 | 6 412 - 8 112 | 4 | 4 | 3/2024 | 8/2028 (+5,1) | ||||
2 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 5 938 - 12 956 | 7 234 | 4 | 3 | 2/2028 | 7/2033 (+4,3) | ||||
3 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 1 942 - 3 996 | 2 561 - 5 054 | 4 | 3 | 2/2028 | 7/2033 (+4,3) | ||||
4 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 16 131 | 9 704 - 13 715 | 4 | 4 | 3/2029 | 5/2033 (+10,2) | ||||
5 | 62. - 63. | 10/2032 | D2 | 8,5 km | 6 | 90 mil. € | 41 057 | 32 968 | . . . | 5 | 5 | 1/2030 | 10/2035 (+5,6) | |||
6 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 46 864 | 5 | 5 | 1/2030 | 10/2035 (+5,9) | |||||
6 úsekov |
57,9 km |
2 - 6 |
1 064 mil. € |
2 561 - 32 968 | 4,3 |
4,0 |
8/2028 - 10/2035 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku