dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
1 | 28. - 29. | 8/2026 | ![]() | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 2 | 2 | 8/2029 (+3,8) | |||||
2 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 2 | Gombasek | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | ||||
3 | 62. - 63. | 10/2032 | ![]() | D2 | 8,5 km | 6 | Stupava | 90 mil. € | 32 968 | . . . | 5 | 5 | 10/2035 (+5,6) | |||
4 | 69. - 70. | 8/2034 | ![]() | R3 | 14,0 km | 2 | Sklené | 305 mil. € | 3 | 3 | 8/2037 (+5,9) | |||||
5 | 69. - 70. | 8/2034 | ![]() | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | |||||
6 | 71. - 78. | po 2040 | ![]() | R3 | 58,5 km | 2 | Devičie, Dolné Semerovce | 611 mil. € | 3 247 - 11 434 | 4 | 4 | po 2040 (+13,9) | ||||
6 úsekov |
152,0 km |
2 - 6 |
1 949 mil. € |
3 247 - 32 968 | 3,8 |
3,8 |
8/2029 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku