dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
11 úsekov |
188,0 km |
2 - 6 |
3 763 mil. € |
4 151 - 29 988 | 3,4 |
3,4 |
4/2029 - 8/2036 |
||||||||
1 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | 107 mil. € | 5 | 5 | 10/2035 (+5,9) | ||||||
2 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 227 mil. € | 4 | 4 | 4/2029 (+4,1) | ||||||
3 | 60. - 61. | 8/2031 | R3 | 8,7 km | 2 | 94 mil. € | 7 211 | 4 | 2 | 8/2034 (+2,1) | |||||
4 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 4 | 4 | 5/2033 (+10,2) | |||||
5 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 5/2033 (+10,2) | |||||
6 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||||
7 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 6/2034 (+7,0) | |||||
8 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 6/2036 (+2,3) | |||||
9 | 60. - 61. | 8/2031 | R3 | 10,9 km | 2 | 129 mil. € | 5 586 - 10 745 | 3 | 2 | 8/2034 (+2,1) | |||||
10 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 8/2036 (+7,9) | |||||
11 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 7/2034 (+10,0) | |||||
11 úsekov |
188,0 km |
2 - 6 |
3 763 mil. € |
4 151 - 29 988 | 3,4 |
3,4 |
4/2029 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku