dátum |
plánovaný
|
odhad NDS
|
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 6/2014 | D3 | 4,3 km | 4 | Brodno - dočasná | 269 mil. € | 28 413 - 37 927 | . . . | 2 | 12/2017 | ||||
2 | 7/2016 | D4 | 4,4 km | 4 - 6 | Čierna voda, Rača | 2 | ||||||||
3 | 7/2016 | D4 | 22,6 km | 4 - 6 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 32 336 - 93 344 | . . . | 2 | ||||||
4 | 7/2016 | R7 | 6,4 km | 4 - 6 | Prievoz | 27 633 - 44 493 | . . . | 1 | 10/2021 | |||||
5 | 3/2020 | R2 | 9,1 km | 4 | Kriváň | 267 mil. € | 8 780 - 11 203 | 4 | 6/2018 | |||||
6 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | Zemné | 227 mil. € | 4 | 2/2024 | |||||
7 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | Mliečany s II/507, Dolný Bar | 161 mil. € | 6 403 - 9 478 | 5 | 4/2024 | ||||
8 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | Moldava nad Bodvou, Šaca | 224 mil. € | 10 140 - 11 010 | 5 | 12/2025 | ||||
96,7 km |
2 - 6 |
1 148 mil. € |
6 403 - 93 344 | 3,1 |
6/2018 - 12/2025 |
12/2017 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku