✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||||
1 | 6/2014 | D3 | 4,3 km | 4 | Brodno - dočasná | 269 mil. € | 28 413 - 37 927 | . . . | 4 | 2 | 12/2017 | ||||||
2 | 7/2016 | D4 | 4,4 km | 4 - 6 | Čierna voda, Rača | 1 | 2 | 11/2015 | |||||||||
3 | 7/2016 | D4 | 22,6 km | 4 - 6 | Jarovce, Rusovce, Ketelec, Rovinka, Ivanka západ, Ivanka sever | 32 336 - 93 344 | . . . | 1 | 2 | 11/2015 | |||||||
4 | 7/2016 | R7 | 6,4 km | 4 - 6 | Prievoz | 16,0 min. | 27 633 - 44 493 | . . . | 1 | 1 | 2/2017 | 10/2021 | |||||
5 | 3/2020 | R2 | 9,1 km | 4 | Kriváň | 267 mil. € | 7,0 min. | 8 780 - 11 203 | 3 | 4 | 6/2018 | ||||||
6 | 6. | 7/2023 | R2 | 6,8 km | 4 | Ludvíkov Dvor, Haniska | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 8/2018 | 7/2022 | |||||
53,6 km |
4 - 6 |
708 mil. € |
23,0 min. |
8 780 - 93 344 | 2,2 |
2,3 |
6/2018 - 7/2022 |
12/2017 - 10/2021 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku