dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
1 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 12/1997 | 1/2029 (+3,0) | ||||
2 | 27. | 5/2026 | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 7/1997 | 5/2029 (+5,1) | ||||
3 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | 2 | 12/1997 | 11/2030 (+6,4) | ||||
4 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 63 mil. € | 9 492 - 10 279 | 3 | 2 | 11/2018 | 11/2030 (+5,2) | ||||
5 | 57. - 58. | 6/2031 | R8 | 54,9 km | 4 | 1 020 mil. € | 4 151 - 11 477 | 3 | 5 | 4/2010 | 6/2036 (+2,3) | ||||
6 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 5 | 5 | po 2040 (0,0) | |||||
89,0 km |
2 - 4 |
2 041 mil. € |
4 151 - 21 743 | 2,5 |
3,2 |
1/2029 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku