dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 25. | 1/2026 | D3 | 10,8 km | 4 | Krásno nad Kysucou | 309 mil. € | 14 176 - 14 186 | 875 - 929 | 2 | 4 | 6/2008 | 8. | ||||
2 | 27. | 5/2026 | D3 | 11,2 km | 4 | Brodno, Kysucké Nové Mesto | 410 mil. € | 13 886 - 21 743 | 738 - 1 705 | 1 | 1 | 10/2010 | 3. | ||||
3 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 018 | 1 | 2 | 8/2013 | 4. | |||||
4 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | Giraltovce | 124 mil. € | 3 769 - 3 897 | 240 - 264 | 3 | 3 | 6/2025 | 45. | ||||
5 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 633 - 797 | 4 | 4 | 5/2028 | 11. | |||||
6 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 476 - 755 | 5 | 5 | 10/2011 | ||||||
46,1 km |
2 - 4 |
1 421 mil. € |
3 769 - 21 743 | 2,7 |
3,2 |
3. - 45. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku