dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 6. | 7/2023 | R2 | 6,8 km | 4 | 2 725 m | 171 mil. € | 11 764 - 50 895 | 169 - 482 | 3 | 3 | 6/2014 | ||||
2 | 25. | 1/2026 | D3 | 10,8 km | 4 | 2 060 m | 309 mil. € | 14 176 - 14 186 | 62 - 103 | 2 | 4 | 12/1997 | ||||
3 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 2 956 m | 199 mil. € | 5 550 - 9 787 | 88 - 175 | 2 | 3 | 8/2006 | ||||
4 | 31. | 11/2026 | D3 | 4,0 km | 4 | 624 m | 179 mil. € | 15 053 | 564 | 1 | 2 | 12/1997 | ||||
5 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 55 - 160 | 5 | 5 | ||||||
6 | 27. | 5/2026 | D3 | 11,2 km | 4 | 3 896 m | 410 mil. € | 13 886 - 21 743 | 118 - 245 | 1 | 1 | 7/1997 | ||||
44,2 km |
2 - 4 |
12 262 m |
1 328 mil. € |
5 420 - 50 895 | 2,3 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku