plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
skutočnosť podľa zmluvy
|
odhad INEKO
| |||||||||
12 úsekov |
163,7 km |
2 - 6 |
3 402 mil. € |
5 762 - 21 743 | 2,7 |
3,2 |
||||||||
1 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | ||||||||
2 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | ||||||||
3 | D4 | 4,4 km | 4 - 6 | 1 | 2 | 6/2016 | 11/2021 | |||||||
4 | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 | 4 | |||||||
5 | R4 | 4,0 km | 4 | 105 mil. € | 14 625 | 2 | 2 | |||||||
6 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | |||||||
7 | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 3 | 5 | |||||||
8 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | |||||||
9 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | 2 | |||||||
10 | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 4 | 4 | |||||||
11 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 4 | 3 | |||||||
12 | D3 | 11,2 km | 4 | 410 mil. € | 13 886 - 21 743 | 1 | 1 | |||||||
12 úsekov |
163,7 km |
2 - 6 |
3 402 mil. € |
5 762 - 21 743 | 2,7 |
3,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku