dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 1 018 m | 173 mil. € | 12 387 - 17 316 | 2 | 3 | 4/2026 (+3,7) | ||||
2 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 68 m | 105 mil. € | 5 304 | 2 | 2 | 3/2026 (+4,7) | ||||
3 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 8/2036 (+7,9) | ||||
4 | 25. | 1/2026 | D3 | 10,8 km | 4 | 804 m | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 1/2029 (+3,0) | ||||
5 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 1 | 2 | 11/2030 (+6,4) | |||||
6 | 4. | 9/2022 | R4 | 10,2 km | 4 | 206 m | 299 mil. € | 22 341 - 30 731 | 1 | 3 | 1/2027 (+4,8) | ||||
7 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | 60 m | 272 mil. € | 5 792 - 7 064 | 3 | 2 | 12/2029 (+5,4) | ||||
8 | 13. | 8/2024 | R2 | 8,3 km | 2 | 57 m | 169 mil. € | 5 277 - 6 250 | 2 | 2 | 8/2026 (+5,1) | ||||
9 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 157 m | 63 mil. € | 9 492 - 10 279 | 3 | 2 | 11/2030 (+5,2) | ||||
10 | 27. | 5/2026 | D3 | 11,2 km | 4 | 1 124 m | 410 mil. € | 13 886 - 21 743 | 1 | 1 | 5/2029 (+5,1) | ||||
10 úsekov |
96,1 km |
2 - 4 |
3 901 m |
2 172 mil. € |
5 277 - 30 731 | 1,9 |
2,3 |
3/2026 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku