dátum |
plánovaný
|
odhad NDS
|
- predĺženie
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
1 | 3. | 3/2022 | ![]() | D1 | 8 | 149 mil. € | 94 554 | 62 652 | . . . | 1 | 1 | |||
2 | 4. | 9/2022 | ![]() | R4 | 4 | 299 mil. € | 12 070 | 22 341 - 30 731 | 1 | 3 | ||||
3 | 5. | 4/2023 | ![]() | R1 | 4 | 173 mil. € | 38 235 | 12 387 - 17 316 | 2 | 3 | ||||
4 | 8. - 9. | 3/2024 | ![]() | R2 | 2 | 105 mil. € | 0,0 km | 6 705 | 5 304 | 2 | 2 | |||
5 | 13. | 8/2024 | ![]() | R2 | 2 | 169 mil. € | 0,0 km | 7 668 | 5 277 - 6 250 | 2 | 2 | |||
6 | 16. - 17. | 12/2024 | ![]() | R2 | 2 | 272 mil. € | 3,4 km | 6 302 | 5 792 - 7 064 | 3 | 2 | |||
7 | 20. - 23. | 10/2025 | ![]() | R3 | 2 | 77 mil. € | 0,9 km | 5 660 | 2 | 2 | ||||
8 | 25. | 1/2026 | ![]() | D3 | 4 | 309 mil. € | 0,0 km | 28 654 | 14 176 - 14 186 | 2 | 4 | |||
9 | 27. | 5/2026 | ![]() | D3 | 4 | 410 mil. € | 0,1 km | 38 080 | 13 886 - 21 743 | 1 | 1 | |||
10 | 31. | 11/2026 | ![]() | D3 | 4 | 179 mil. € | 0,0 km | 26 769 | 15 053 | 1 | 2 | |||
2 - 8 |
2 142 mil. € |
4,4 km |
5 277 - 62 652 | 1,7 |
2,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku