dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
1 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | 70 mil. € | 742 - 818 | 2 | 2 | 6,0 | |||
2 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | 309 mil. € | 2 105 - 2 649 | 2 | 4 | 6,0 | |||
3 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 863 - 1 016 | 4 | 4 | 5,0 | |||
4 | 27. | 5/2026 | ![]() | D3 | 11,2 km | 4 | 410 mil. € | 2 661 - 2 869 | 1 | 1 | 7,0 | |||
5 | 28. - 29. | 8/2026 | ![]() | R4 | 4,0 km | 4 | 105 mil. € | 1 056 | 2 | 2 | 5,0 | |||
6 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 655 - 822 | 4 | 4 | 5,0 | |||
7 | 30. | 10/2026 | ![]() | R1 | 4,6 km | 4 | 100 mil. € | 693 | 4 | 3 | 3,0 | |||
8 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 2 660 | 1 | 2 | 7,0 | |||
9 | 32. - 33. | 12/2026 | ![]() | R2 | 18,0 km | 2 | 224 mil. € | 792 - 846 | 3 | 5 | 5,0 | |||
9 úsekov |
90,4 km |
2 - 4 |
1 732 mil. € |
2,6 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku