dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 449 m | 112 mil. € | 8 634 - 11 116 | 2 | 4 | ||||||
2 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 7,3 km | 5 587 | 5 | 4 | ||||||
3 | 41. | 9/2028 | R2 | 11,5 km | 2 | 214 m | 235 mil. € | 12,1 km | 7 793 | 2 | 4 | |||||
4 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 446 m | 785 mil. € | 8 140 - 13 204 | 3 | 3 | ||||||
5 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 199 m | 101 mil. € | 6,3 km | 3 782 - 6 302 | 4 | 3 | |||||
6 | 42. - 43. | 11/2028 | R3 | 5,0 km | 2 | 157 m | 63 mil. € | 9 492 - 10 279 | 3 | 2 | ||||||
7 | 42. - 43. | 11/2028 | R4 | 7,9 km | 2 | 164 m | 129 mil. € | 8,0 km | 2 552 - 2 737 | 4 | 3 | |||||
8 | 27. | 5/2026 | D3 | 11,2 km | 4 | 1 124 m | 410 mil. € | 11,3 km | 13 886 - 21 743 | 1 | 1 | |||||
73,9 km |
2 - 4 |
2 752 m |
1 908 mil. € |
45,0 km |
2 552 - 21 743 | 3,0 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku