dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
20 úsekov |
305,0 km |
2 - 6 |
5 785 mil. € |
3 247 - 14 648 | 3,6 |
4,0 |
7/2024 - po 2040 | ||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||||
2 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | Nováky - západ | 112 mil. € | 8 634 - 11 116 | 2 | 4 | 3/2031 (+5,9) | ||||
3 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | Zemné | 227 mil. € | 4 | 4 | 4/2029 (+4,1) | |||||
4 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | Jablonov n.Turňou | 73 mil. € | 5 587 | 5 | 4 | 2/2031 (+4,1) | ||||
5 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | Liptovská Osada | 406 mil. € | 7 784 | 4 | 4 | 5/2033 (+10,2) | ||||
6 | 3/2020 | R2 | 9,1 km | 4 | Kriváň | 267 mil. € | 8 780 - 11 203 | 3 | 4 | 2024 (+2,8) | |||||
7 | 24. | 12/2025 | R2 | 6,1 km | 4 | Trenčín juh, Trenčianska Turná | 143 mil. € | 12 157 | 3 | 4 | 2/2023 | 12/2028 (+4,3) | |||
8 | 25. | 1/2026 | D3 | 10,8 km | 4 | Krásno nad Kysucou | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 2/2024 | 1/2029 (+3,0) | |||
9 | 55. - 56. | 5/2031 | R1 | 9,5 km | 4 | 339 mil. € | 9 704 - 13 715 | 4 | 4 | 5/2033 (+10,2) | |||||
10 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 4/2028 (+4,8) | |||||
11 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | Prievidza, Brusno, Handlová, Nová Lehota | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||
12 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | Rimavská Sobota | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 8/2028 (+5,1) | ||||
13 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 7 793 | 2 | 4 | 9/2031 (+5,4) | |||||
14 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | Slovenská Ľupča, Korytnica | 785 mil. € | 8 140 - 13 204 | 3 | 3 | 2/2031 (+6,9) | ||||
15 | 62. - 63. | 10/2032 | D2 | 6,9 km | 6 | Stupava | 107 mil. € | 5 | 5 | 10/2035 (+5,9) | |||||
16 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | Svrčinovec, Svrčinovec - hranica | 54 mil. € | 7 972 | 3 | 4 | 3/2025 (0,0) | ||||
17 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 9/2022 | 10/2028 (+4,2) | ||||
18 | 47. | 7/2029 | R2 | 14,0 km | 2 | Turňa nad Bodvou | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 7/2032 (+5,3) | ||||
19 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | Nové Zámky | 172 mil. € | 4 | 4 | 4/2029 (+4,1) | |||||
20 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | Budča, privádzače D. Niva, Babiná, Hont. Nemce, Dudince, Semerovce | 611 mil. € | 3 247 - 11 434 | 4 | 4 | po 2040 (+13,9) | ||||
20 úsekov |
305,0 km |
2 - 6 |
5 785 mil. € |
3 247 - 14 648 | 3,6 |
4,0 |
7/2024 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku