dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | D 26,5/120 (tunel 2 x T 8,0/100) | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | |||||
2 | 7/2016 | D4 | 22,6 km | 4 - 6 | D 33,5/120, D 26,5/120 | 32 336 - 93 344 | . . . | 1 | 2 | 11/2021 (+0,4) | |||||
3 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | R 24,5/80 | 406 mil. € | 7 784 | 4 | 4 | 5/2033 (+10,2) | ||||
4 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 1/2029 (+3,0) | ||||
5 | 8/2019 | R2 | 13,5 km | 4 | R 24,5/100 | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 2021 (+1,1) | |||||
6 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | R 11,5/120 | 230 mil. € | 2 156 - 6 890 | 5 | 5 | po 2040 (0,0) | ||||
6 úsekov |
100,1 km |
2 - 6 |
1 858 mil. € |
2 156 - 93 344 | 2,8 |
3,5 |
7/2021 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku