dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 8/2007 | 6/2033 (+3,3) | ||||
2 | 60. - 61. | 8/2031 | ![]() | R3 | 8,7 km | 2 | 94 mil. € | 7 211 | 4 | 2 | 5/2007 | 8/2034 (+2,1) | |||
3 | 25. | 1/2026 | ![]() | D3 | 10,8 km | 4 | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 7/1996 | 1/2029 (+3,0) | |||
4 | 11. | 6/2024 | ![]() | R1 | 2,7 km | 4 | 155 mil. € | 16 268 | 4 | 3 | 9/2009 | 6/2026 (+3,5) | |||
5 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 7/2010 | 2/2032 (+4,9) | |||
6 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 4 | 3 | 4/2005 | 7/2033 (+4,3) | |||
6 úsekov |
63,9 km |
2 - 4 |
1 728 mil. € |
2 561 - 16 268 | 3,7 |
3,5 |
6/2026 - 8/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku