dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
1 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 269 - 3 025 | 2 | 2 | 22 | 10/2028 (+3,2) | ||||
2 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 2 829 | 3 | 4 | 23 | 10/2028 (+4,2) | ||||
3 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 2 815 | 3 | 4 | 24 | 12/2028 (+4,3) | ||||
4 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 4 830 | 1 | 2 | 31 | 11/2030 (+6,4) | ||||
5 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 45 | 2/2033 (+4,5) | ||||||
6 | 50. - 52. | 5/2030 | ![]() | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 1 697 - 2 149 | 4 | 3 | 52 | 5/2033 (+6,1) | ||||
7 | 64. - 68. | 8/2033 | ![]() | D1 | 15,8 km | 4 | 139 mil. € | 4 033 - 8 369 | 678 - 970 | 4 | 3 | 66 | 8/2036 (+7,7) | ||||
7 úsekov |
54,1 km |
2 - 4 |
1 030 mil. € |
3 782 - 15 053 | 3,1 |
3,3 |
22 - 66 |
10/2028 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku