dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||
1 | 7/2016 | ![]() | R7 | 6,4 km | 4 - 6 | 912 - 1 523 | 1 | 1 | 10/2021 (+0,3) | 10/2021 | ||||
2 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | 277 mil. € | 1 040 - 1 450 | 2 | 2 | 10/2028 (+3,2) | |||
3 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 1 313 | 3 | 4 | 10/2028 (+4,2) | |||
4 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 1 263 | 3 | 4 | 12/2028 (+4,3) | |||
5 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 2 660 | 1 | 2 | 11/2030 (+6,4) | |||
6 | 34. - 36. | 6/2027 | ![]() | R4 | 7,0 km | 2 | 122 mil. € | 1 103 - 1 149 | 2 | 2 | 6/2030 (+3,7) | |||
7 | 37. - 38. | 2/2028 | ![]() | R1 | 14,9 km | 4 | 785 mil. € | 544 - 944 | 3 | 3 | 2/2031 (+6,9) | |||
7 úsekov |
57,0 km |
2 - 6 |
1 564 mil. € |
2,1 |
2,6 |
10/2021 - 2/2031 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku