dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka | ||||||||||
1 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | Kuková | 116 mil. € | 6 651 - 9 113 | 1 133 - 1 196 | 2 | ||||
2 | 24. | 12/2025 | R2 | 6,1 km | 4 | Trenčín juh, Trenčianska Turná | 143 mil. € | 12 157 | 2 815 | 3 | ||||
3 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 9 654 - 12 079 | 2 269 - 3 025 | 2 | ||||
4 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | Bešeňov, Čaka | 230 mil. € | 2 156 - 6 890 | 607 - 1 070 | 5 | ||||
5 | 31. | 11/2026 | D3 | 4,0 km | 4 | 179 mil. € | 15 053 | 4 830 | 1 | |||||
6 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 2 829 | 3 | |||||
7 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | Kľačany, Lučenec Západ, Lučenec Východ | 367 mil. € | 2 228 - 6 331 | 328 - 768 | 5 | ||||
97,3 km |
2 - 4 |
1 370 mil. € |
2 156 - 15 053 | 3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku