dátum |
plánovaný
|
odhad NDS
|
- predĺženie
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 14. - 15. | 10/2024 | R7 | 14,3 km | 2 | 172 mil. € | 4 | 4 | 6,0 | ||||||||
2 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 230 mil. € | 2 156 - 6 890 | 5 | 5 | 4,0 | |||||||
3 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 92 mil. € | 5,8 % (Martin - Horná Štubňa) | 5 098 - 5 557 | 4 | 2 | 4,0 | ||||||
4 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 5 | 5 | 5,0 | |||||||
5 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 54 mil. € | 7 972 | 3 | 4 | 4,0 | |||||||
6 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 367 mil. € | 2 228 - 6 331 | 5 | 5 | 2,0 | |||||||
7 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | 611 mil. € | -1,3 % (Zvolen-Šahy) | 3 247 - 11 434 | 4 | 4 | 2,0 | ||||||
8 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 553 mil. € | 1 065 - 4 239 | 5 | 5 | 2,0 | |||||||
8 úsekov |
221,1 km |
2 - 4 |
2 140 mil. € |
1 065 - 11 434 | 4,4 |
4,3 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku