dátum |
plánovaný
|
odhad NDS
|
podľa údajov NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 1 397 m | 173 mil. € | 12 387 - 17 316 | 2 | 3 | |||||
2 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 1 929 m | 277 mil. € | 9 654 - 12 079 | 2 | 2 | |||||
3 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 1 216 m | 101 mil. € | 3 782 - 6 302 | 4 | 3 | |||||
4 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 631 mil. € | 5 713 - 13 545 | 5 | 5 | ||||||
5 | 71. - 78. | po 2040 | R7 | 29,2 km | 2 | 3 494 m | 230 mil. € | 2 156 - 6 890 | 5 | 5 | |||||
6 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | 395 m | 92 mil. € | 5 098 - 5 557 | 4 | 2 | |||||
7 | 71. - 78. | po 2040 | D3 | 3,1 km | 4 | 60 mil. € | 5 420 - 8 693 | 5 | 5 | ||||||
8 | 71. - 78. | po 2040 | R7 | 32,8 km | 2 | 6 851 m | 367 mil. € | 2 228 - 6 331 | 5 | 5 | |||||
9 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | 14 945 m | 611 mil. € | 3 247 - 11 434 | 4 | 4 | |||||
10 | 71. - 78. | po 2040 | R7 | 71,3 km | 2 | 9 563 m | 553 mil. € | 1 065 - 4 239 | 5 | 5 | |||||
277,4 km |
2 - 4 |
39 790 m |
3 095 mil. € |
1 065 - 17 316 | 4,1 |
3,9 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku