dátum |
plánovaný
|
odhad NDS
|
na aktuálne plánovaný počet jazdných pruhov
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 12/2013 | D1 | 14,9 km | 4 | 341 mil. € | 288 mil. € | 17,0 km | 12 491 - 24 900 | 1 | 1 | ||||||
2 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 234 mil. € | 15,4 km | 9 654 - 12 079 | 2 | 2 | |||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 118 mil. € | 8,9 km | 5 814 - 7 518 | 4 | 3 | |||||
4 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 110 mil. € | 8,3 km | 3 769 - 3 897 | 3 | 3 | |||||
5 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 87 mil. € | 6,3 km | 3 782 - 6 302 | 4 | 3 | |||||
6 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 161 mil. € | 7 234 | 4 | 3 | ||||||
7 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 199 mil. € | 2 561 - 5 054 | 4 | 3 | ||||||
8 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 54 mil. € | 49 mil. € | 7 972 | 3 | 4 | ||||||
8 úsekov |
76,6 km |
2 - 4 |
1 434 mil. € |
1 246 mil. € |
55,9 km |
2 561 - 24 900 | 3,1 |
2,8 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku