dátum |
plánovaný
|
odhad NDS
|
rok
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | ||||||||||
1 | 12. | 7/2024 | R3 | 6,5 km | 2 | 0 m | 70 mil. € | 2030 | 6 706 - 9 733 | 2 | 2 | 7/2026 (+2,7) | |||||
2 | 14. - 15. | 10/2024 | R7 | 23,5 km | 2 | 0 m | 227 mil. € | 2030 | 4 | 4 | 4/2029 (+4,1) | ||||||
3 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | 0 m | 161 mil. € | 2030 | 6 403 - 9 478 | 4 | 5 | 5/2029 (+3,5) | |||||
4 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 0 m | 224 mil. € | 2030 | 10 140 - 11 010 | 3 | 5 | 12/2029 (+2,8) | |||||
5 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 0 m | 101 mil. € | 2030 | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | |||||
6 | 71. - 78. | po 2040 | R5 | 1,7 km | 2 | 0 m | 54 mil. € | 2030 | 7 972 | 3 | 4 | 3/2025 (0,0) | |||||
64,2 km |
2 - 4 |
837 mil. € |
3 782 - 11 010 | 3,3 |
3,8 |
3/2025 - 5/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku