✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | ✖ | |||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
# |
dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
1 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 142 - 701 | 4 | 3 | ||||
2 | 53. - 54. | 7/2030 | R6 | 11,2 km | 2 | 182 mil. € | 7 234 | 394 | 4 | 3 | ||||
3 | 50. - 52. | 5/2030 | R4 | 7,5 km | 2 | 124 mil. € | 3 769 - 3 897 | 1 149 - 1 405 | 3 | 3 | ||||
4 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 1 375 - 1 435 | 4 | 3 | ||||
5 | 53. - 54. | 7/2030 | R6 | 11,3 km | 2 | 222 mil. € | 2 561 - 5 054 | 292 - 307 | 4 | 3 | ||||
6 | 39. - 40. | 3/2028 | D1 | 19,9 km | 6 | 321 mil. € | 42 774 - 54 519 | . . . | 3 137 - 3 460 | 3 | 2 | |||
7 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 62 652 | . . . | 4 737 | 2 | 1 | |||
7 úsekov |
74,5 km |
2 - 8 |
1 317 mil. € |
2 561 - 62 652 | 3,4 |
2,6 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku