dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
204,5 km |
2 - 8 |
3 726 mil. € |
2,1 |
2,4 |
8/2017 - 8/2032 |
||||||||
1 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 4 | 3 | 10/2010 | 2/2026 | |||
2 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 418 mil. € | 3 | 3 | 3/1998 | 8/2032 | |||
3 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 2 | 3 | 10/2010 | 8/2022 | |||
4 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 2 | 1 | 5/2010 | 10/2026 | |||
5 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 105 mil. € | 2 | 2 | 10/2005 | 7/2023 | |||
6 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 2 | 2 | 4/1998 | 8/2032 | |||
7 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 5/2007 | 2/2025 | |||
8 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 112 mil. € | 2 | 4 | 2/2006 | 7/2027 | |||
9 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 116 mil. € | 2 | 3 | 12/2017 | 6/2026 | |||
10 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 2 | 1 | 10/2014 | 12/2018 | |||
11 | 12. | 7/2024 | R3 | 6,5 km | 2 | 70 mil. € | 2 | 2 | 3/2021 | 12/2023 | |||
12 | 25. | 1/2026 | D3 | 10,8 km | 4 | 309 mil. € | 2 | 4 | 11/2000 | 5/2025 | |||
13 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 105 mil. € | 2 | 2 | 12/2017 | 8/2025 | |||
14 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 2 | 2 | 10/2005 | 2/2025 | |||
15 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 2 | 2 | 2/2006 | 2/2018 | ||||
16 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 199 mil. € | 2 | 3 | 5/2007 | 2/2025 | |||
17 | 41. | 9/2028 | R2 | 11,5 km | 2 | 235 mil. € | 2 | 4 | 2/2006 | 1/2028 | |||
18 | 18. | 4/2025 | D1 | 1,1 km | 2 | 12 mil. € | 2 | 1 | 6/2005 | 4/2024 | |||
19 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 122 mil. € | 2 | 2 | 12/2017 | 6/2026 | |||
20 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 2 | 2 | 5/2007 | 8/2017 | ||||
21 | 13. | 8/2024 | R2 | 8,3 km | 2 | 169 mil. € | 2 | 2 | 10/2005 | 12/2023 | |||
22 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 2 | 2 | 3/2009 | 11/2030 | |||
204,5 km |
2 - 8 |
3 726 mil. € |
2,1 |
2,4 |
8/2017 - 8/2032 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku