dátum |
plánovaný
|
odhad NDS
|
stavebné práce
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||||
21 úsekov |
199,9 km |
2 - 8 |
6 279 m |
3 626 mil. € |
3 407 - 62 652 | 2,0 |
2,3 |
7/2021 - 8/2036 |
||||||||||
1 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 2021 (+1,1) | |||||||||
2 | 3/2021 | R3 | 4,4 km | 2 | 135 m | 70 mil. € | 10 334 - 11 542 | 2 | 2 | 8/2022 (+2,2) | ||||||||
3 | 1. | 10/2021 | R4 | 14,3 km | 4 | 365 m | 202 mil. € | 10 088 - 50 895 | 2 | 1 | 10/2024 (+2,6) | |||||||
4 | 5. | 4/2023 | R1 | 8,1 km | 4 | 1 018 m | 173 mil. € | 12 387 - 17 316 | 2 | 3 | 4/2026 (+3,7) | |||||||
5 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | 68 m | 105 mil. € | 5 304 | 2 | 2 | 3/2026 (+4,7) | |||||||
6 | 12. | 7/2024 | R3 | 6,5 km | 2 | 428 m | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 7/2026 (+2,7) | |||||||
7 | 13. | 8/2024 | R2 | 8,3 km | 2 | 57 m | 169 mil. € | 5 277 - 6 250 | 2 | 2 | 8/2026 (+5,1) | |||||||
8 | 18. | 4/2025 | D1 | 1,1 km | 2 | 126 m | 12 mil. € | 2 | 1 | 1/2027 (+5,0) | ||||||||
9 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 0 m | 77 mil. € | 2 | 2 | 10/2028 (+4,1) | ||||||||
10 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | 192 m | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 10/2028 (+4,1) | |||||||
11 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 496 m | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 10/2028 (+3,2) | |||||||
12 | 25. | 1/2026 | D3 | 10,8 km | 4 | 804 m | 309 mil. € | 14 176 - 14 186 | 2 | 4 | 1/2029 (+3,0) | |||||||
13 | 28. - 29. | 8/2026 | R4 | 4,0 km | 4 | 578 m | 105 mil. € | 14 625 | 2 | 2 | 8/2029 (+3,8) | |||||||
14 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 331 m | 234 mil. € | 62 652 | . . . | 2 | 1 | 6/2030 (+6,9) | ||||||
15 | 34. - 36. | 6/2027 | R4 | 6,5 km | 2 | 101 m | 116 mil. € | 6 651 - 9 113 | 2 | 3 | 6/2030 (+3,7) | |||||||
16 | 34. - 36. | 6/2027 | R4 | 7,0 km | 2 | 227 m | 122 mil. € | 3 407 - 3 769 | 2 | 2 | 6/2030 (+3,7) | |||||||
17 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | 449 m | 112 mil. € | 8 634 - 11 116 | 2 | 4 | 3/2031 (+5,9) | |||||||
18 | 41. | 9/2028 | R2 | 11,5 km | 2 | 214 m | 235 mil. € | 7 793 | 2 | 4 | 9/2031 (+5,4) | |||||||
19 | 59. | 7/2031 | R2 | 17,5 km | 4 | 228 m | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 7/2034 (+10,0) | |||||||
20 | 64. - 68. | 8/2033 | D1 | 12,6 km | 4 | 53 m | 418 mil. € | 9 503 - 9 802 | 3 | 3 | 8/2036 (+7,9) | |||||||
21 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 408 m | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 8/2036 (+7,9) | |||||||
21 úsekov |
199,9 km |
2 - 8 |
6 279 m |
3 626 mil. € |
3 407 - 62 652 | 2,0 |
2,3 |
7/2021 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku