dátum |
plánovaný
|
jednostranné / obojstranné
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka | |||||||
25 úsekov |
240,0 km |
2 - 8 |
6 124 mil. € |
3,2 |
||||||||
1 | 46. | 3/2029 | ![]() | D1 | 7,3 km | 4 | 321 mil. € | 3 | ||||
2 | 39. - 40. | 3/2028 | ![]() | D1 | 19,9 km | 6 | Zeleneč rekonštrukcia, obojstranné | 321 mil. € | 3 | |||
3 | 34. - 36. | 6/2027 | ![]() | D1 | 10,6 km | 8 | 234 mil. € | 2 | ||||
4 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | ||||
5 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | ||||
6 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | ||||
7 | 39. - 40. | 3/2028 | ![]() | R2 | 9,6 km | 2 | 112 mil. € | 2 | ||||
8 | 34. - 36. | 6/2027 | ![]() | R4 | 6,5 km | 2 | Giraltovce, jednostranné | 116 mil. € | 2 | |||
9 | 48. - 49. | 9/2029 | ![]() | R2 | 9,8 km | 2 | 93 mil. € | 5 | ||||
10 | 37. - 38. | 2/2028 | ![]() | R2 | 7,8 km | 2 | 73 mil. € | 5 | ||||
11 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 133 mil. € | 4 | ||||
12 | 53. - 54. | 7/2030 | ![]() | R6 | 11,2 km | 2 | 182 mil. € | 4 | ||||
13 | 48. - 49. | 9/2029 | ![]() | R3 | 7,9 km | 2 | 71 mil. € | 4 | ||||
14 | 31. | 11/2026 | ![]() | D3 | 4,0 km | 4 | 179 mil. € | 1 | ||||
15 | 41. | 9/2028 | ![]() | R2 | 11,5 km | 2 | Jerichov | 235 mil. € | 2 | |||
16 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 2 | 124 mil. € | 3 | ||||
17 | 34. - 36. | 6/2027 | ![]() | R4 | 7,0 km | 2 | 122 mil. € | 2 | ||||
18 | 37. - 38. | 2/2028 | ![]() | R1 | 14,9 km | 4 | 785 mil. € | 3 | ||||
19 | 50. - 52. | 5/2030 | ![]() | R4 | 6,0 km | 2 | 101 mil. € | 4 | ||||
20 | 44. - 45. | 2/2029 | ![]() | R2 | 18,0 km | 2 | Gombasek | 176 mil. € | 5 | |||
21 | 7. | 2/2024 | ![]() | D1 | 13,5 km | 4 | 1 235 mil. € | 1 | ||||
22 | 47. | 7/2029 | ![]() | R2 | 14,0 km | 2 | Drienovec | 117 mil. € | 5 | |||
23 | 42. - 43. | 11/2028 | ![]() | R3 | 5,0 km | 2 | Dolné Semerovce | 63 mil. € | 3 | |||
24 | 42. - 43. | 11/2028 | ![]() | R4 | 7,9 km | 2 | Vyšný Komárnik | 129 mil. € | 4 | |||
25 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | Strelenka, obojstranné | 222 mil. € | 4 | |||
25 úsekov |
240,0 km |
2 - 8 |
6 124 mil. € |
3,2 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku