dátum |
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||
295,1 km |
7 124 mil. € |
2,8 |
3,0 |
|||||||
1 | 7. | 2/2024 | ![]() | 13,5 km | Turany 2, Hubová | 1 235 mil. € | 1 | 1 | ||
2 | 8. - 9. | 3/2024 | ![]() | 9,4 km | Holice s I/63, D. Streda s III/06325 | 191 mil. € | 4 | 5 | ||
3 | 14. - 15. | 10/2024 | ![]() | 23,5 km | Zemné | 227 mil. € | 4 | 4 | ||
4 | 14. - 15. | 10/2024 | ![]() | 14,3 km | Nové Zámky | 172 mil. € | 4 | 4 | ||
5 | 16. - 17. | 12/2024 | ![]() | 14,1 km | Rožňava, Jablonov nad Turňou | 272 mil. € | 3 | 2 | ||
6 | 20. - 23. | 10/2025 | ![]() | 4,9 km | Dlhá nad Oravou | 77 mil. € | 2 | 2 | ||
7 | 20. - 23. | 10/2025 | ![]() | 8,3 km | Podbiel | 199 mil. € | 2 | 3 | ||
8 | 20. - 23. | 10/2025 | ![]() | 16,0 km | Trenčianske Mitice | 277 mil. € | 2 | 2 | ||
9 | 20. - 23. | 10/2025 | ![]() | 2,7 km | 59 mil. € | 3 | 4 | |||
10 | 24. | 12/2025 | ![]() | 6,1 km | Trenčín juh, Trenčianska Turná | 143 mil. € | 3 | 4 | ||
11 | 26. | 4/2026 | ![]() | 20,7 km | 211 mil. € | 4 | 4 | |||
12 | 28. - 29. | 8/2026 | ![]() | 4,0 km | Lipníky | 105 mil. € | 2 | 2 | ||
13 | 28. - 29. | 8/2026 | ![]() | 10,6 km | Rimavská Sobota | 125 mil. € | 4 | 4 | ||
14 | 30. | 10/2026 | ![]() | 4,6 km | križovatka D1 | 100 mil. € | 4 | 3 | ||
15 | 31. | 11/2026 | ![]() | 4,0 km | 179 mil. € | 1 | 2 | |||
16 | 32. - 33. | 12/2026 | ![]() | 12,4 km | 772 mil. € | 3 | 4 | |||
17 | 32. - 33. | 12/2026 | ![]() | 18,0 km | Moldava nad Bodvou, Šaca | 224 mil. € | 3 | 5 | ||
18 | 34. - 36. | 6/2027 | ![]() | 10,6 km | Senec | 234 mil. € | 2 | 1 | ||
19 | 34. - 36. | 6/2027 | ![]() | 6,5 km | Kuková | 116 mil. € | 2 | 3 | ||
20 | 34. - 36. | 6/2027 | ![]() | 7,0 km | Okrúhle | 122 mil. € | 2 | 2 | ||
21 | 37. - 38. | 2/2028 | ![]() | 14,9 km | Slovenská Ľupča, Korytnica | 785 mil. € | 3 | 3 | ||
22 | 37. - 38. | 2/2028 | ![]() | 7,8 km | Jablonov n.Turňou | 73 mil. € | 5 | 4 | ||
23 | 39. - 40. | 3/2028 | ![]() | 19,9 km | Zeleneč nová, Trnava rekonštrukcia | 321 mil. € | 3 | 2 | ||
24 | 41. | 9/2028 | ![]() | 11,5 km | 235 mil. € | 2 | 4 | |||
25 | 42. - 43. | 11/2028 | ![]() | 5,0 km | Šahy | 63 mil. € | 3 | 2 | ||
26 | 46. | 3/2029 | ![]() | 7,3 km | 321 mil. € | 3 | 3 | |||
27 | 59. | 7/2031 | ![]() | 17,5 km | Rákoš, Zvolenská Slatina | 287 mil. € | 2 | 2 | ||
295,1 km |
7 124 mil. € |
2,8 |
3,0 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku