dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
1 | 34. - 36. | 6/2027 | D1 | 10,6 km | 8 | 234 mil. € | 62 652 | . . . | 2 | 1 | 5,0 | 6/2016 | 6/2030 (+6,9) | |||
2 | 64. - 68. | 8/2033 | D1 | 18,2 km | 4 | 192 mil. € | 6 207 - 8 525 | 2 | 2 | 2,0 | 8/2030 | 8/2036 (+7,9) | ||||
3 | 1. | 10/2021 | R4 | 14,3 km | 4 | 202 mil. € | 10 088 - 50 895 | 2 | 1 | 10,0 | 7/2018 | 10/2024 (+2,6) | ||||
4 | 50. - 52. | 5/2030 | R4 | 6,0 km | 2 | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 4,0 | 8/2027 | 5/2033 (+6,1) | ||||
5 | 3/2021 | R3 | 4,4 km | 2 | 70 mil. € | 10 334 - 11 542 | 2 | 2 | 11,0 | 2/2011 | 8/2022 (+2,2) | |||||
5 úsekov |
53,5 km |
2 - 8 |
799 mil. € |
3 782 - 62 652 | 2,4 |
1,8 |
8/2022 - 8/2036 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku