dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 34. - 36. | 6/2027 | ![]() | D1 | 10,6 km | 8 | 0 m | 234 mil. € | 62 652 | . . . | 2 | 1 | 6/2030 (+6,9) | ||
2 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 10 990 m | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||
3 | 37. - 38. | 2/2028 | ![]() | R2 | 7,8 km | 2 | 0 m | 73 mil. € | 5 587 | 5 | 4 | 2/2031 (+4,1) | |||
4 | 50. - 52. | 5/2030 | ![]() | R4 | 8,0 km | 2 | 0 m | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | |||
5 | 41. | 9/2028 | ![]() | R2 | 11,5 km | 2 | 593 m | 235 mil. € | 7 793 | 2 | 4 | 9/2031 (+5,4) | |||
6 | 10. | 4/2024 | ![]() | D1 | 3,8 km | 2 | 0 m | 57 mil. € | 10 312 | 3 | 5 | 4/2027 (+4,1) | |||
6 úsekov |
54,2 km |
2 - 8 |
11 583 m |
1 505 mil. € |
5 587 - 62 652 | 3,2 |
3,5 |
4/2027 - 6/2033 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku