dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | |||||
2 | 7/2016 | D4 | 22,6 km | 4 - 6 | 32 336 - 93 344 | . . . | 1 | 2 | 11/2021 (+0,4) | |||||
3 | 6. | 7/2023 | R2 | 6,8 km | 4 | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 7/2026 (+4,3) | ||||
4 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||
5 | 8/2019 | R2 | 13,5 km | 4 | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 2021 (+1,1) | |||||
6 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | ||||
7 | 59. | 7/2031 | R2 | 17,5 km | 4 | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 7/2034 (+10,0) | ||||
7 úsekov |
98,8 km |
2 - 6 |
1 682 mil. € |
5 189 - 93 344 | 2,9 |
3,0 |
7/2021 - 7/2034 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku