dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
13 úsekov |
176,3 km |
2 - 4 |
3 498 mil. € |
2 228 - 13 545 | 3,5 |
3,8 |
20 - 78 | |||||||
1 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 20 | ||||
2 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 21 | |||
3 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 22 | |||
4 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 23 | |||
5 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 143 mil. € | 12 157 | 3 | 4 | 24 | |||
6 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 26 | |||
7 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 29 | |||
8 | 30. | 10/2026 | ![]() | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 4 | 3 | 30 | |||
9 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 32 | ||||
10 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 45 | ||||
11 | 55. - 56. | 5/2031 | ![]() | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 4 | 4 | 56 | |||
12 | 71. - 78. | po 2040 | ![]() | R1 | 42,1 km | 4 | 631 mil. € | 5 713 - 13 545 | 5 | 5 | 74 | |||
13 | 71. - 78. | po 2040 | ![]() | R7 | 32,8 km | 2 | 367 mil. € | 2 228 - 6 331 | 5 | 5 | 78 | |||
13 úsekov |
176,3 km |
2 - 4 |
3 498 mil. € |
2 228 - 13 545 | 3,5 |
3,8 |
20 - 78 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku