dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | 77 mil. € | 2 | 2 | 9/2009 | 1/2023 | ||||||
2 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 7/2010 | 9/2023 | |||||
3 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 59 mil. € | 12 862 | 3 | 4 | 3/2011 | 10/2022 | |||||
4 | 26. | 4/2026 | R2 | 20,7 km | 2 | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 1/2011 | 11/2023 | |||||
5 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 2/2009 | 3/2024 | |||||
6 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 4 | 3 | 7/2023 | 7/2025 | |||||
7 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 7/2024 | |||||||
8 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 12/2019 | 12/2023 | |||||
9 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | 73 mil. € | 5 587 | 5 | 4 | 7/2020 | 2/2025 | |||||
10 | 44. - 45. | 2/2029 | D4 | 3,6 km | 4 | 133 mil. € | 5 | 5 | 5/2026 | |||||||
10 úsekov |
101,3 km |
2 - 4 |
2 050 mil. € |
5 587 - 12 862 | 3,5 |
3,7 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku