dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||
1 | 50. - 52. | 5/2030 | ![]() | R4 | 7,5 km | 2 | Giraltovce | 124 mil. € | 16,6 mil. € | 3 | 3 | |||
2 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 15,6 mil. € | 2 | 2 | |||
3 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 24,0 mil. € | 2 | 3 | |||
4 | 26. | 4/2026 | ![]() | R2 | 20,7 km | 2 | 211 mil. € | 10,2 mil. € | 4 | 4 | ||||
5 | 20. - 23. | 10/2025 | ![]() | R2 | 16,0 km | 4 | Trenčianske Mitice | 277 mil. € | 17,3 mil. € | 2 | 2 | |||
6 | 28. - 29. | 8/2026 | ![]() | R2 | 10,6 km | 2 | Rimavská Sobota | 125 mil. € | 11,8 mil. € | 4 | 4 | |||
7 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 59 mil. € | 23,3 mil. € | 3 | 4 | ||||
8 | 30. | 10/2026 | ![]() | R1 | 4,6 km | 4 | križovatka D1 | 100 mil. € | 21,7 mil. € | 4 | 3 | |||
9 | 44. - 45. | 2/2029 | ![]() | D4 | 3,6 km | 4 | 133 mil. € | 37,2 mil. € | 5 | 5 | ||||
10 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 772 mil. € | 62,1 mil. € | 3 | 4 | ||||
10 úsekov |
91,3 km |
2 - 4 |
2 076 mil. € |
22,8 mil. € |
3,2 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku