dátum |
plánovaný
|
odhad NDS
|
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky | |||||||||
1 | 8. - 9. | 3/2024 | ![]() | R7 | 9,4 km | 4 | 0 m | 191 mil. € | 6 428 - 9 084 | 5 | 9/2028 (+3,5) | |||
2 | 12. | 7/2024 | ![]() | R3 | 6,5 km | 2 | 0 m | 70 mil. € | 6 706 - 9 733 | 2 | 7/2026 (+2,7) | |||
3 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 0 m | 77 mil. € | 2 | 10/2028 (+4,1) | ||||
4 | 20. - 23. | 10/2025 | ![]() | R3 | 8,3 km | 2 | 630 m | 199 mil. € | 5 550 - 9 787 | 3 | 10/2028 (+4,1) | |||
5 | 20. - 23. | 10/2025 | ![]() | R2 | 2,7 km | 4 | 0 m | 59 mil. € | 12 862 | 4 | 10/2028 (+4,2) | |||
6 | 24. | 12/2025 | ![]() | R2 | 6,1 km | 4 | 0 m | 143 mil. € | 12 157 | 4 | 12/2028 (+4,3) | |||
7 | 32. - 33. | 12/2026 | ![]() | D4 | 12,4 km | 4 | 10 990 m | 772 mil. € | 4 | 6/2033 (+3,3) | ||||
8 | 71. - 78. | po 2040 | ![]() | R3 | 10,3 km | 2 | 0 m | 92 mil. € | 5 098 - 5 557 | 2 | po 2040 (0,0) | |||
60,6 km |
2 - 4 |
11 620 m |
1 602 mil. € |
5 098 - 12 862 | 3,3 |
7/2026 - po 2040 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku