dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 2/2026 | 6/2033 (+3,3) | |||||
2 | 69. - 70. | 8/2034 | R3 | 14,0 km | 2 | 305 mil. € | 3 | 3 | 5/2030 | 8/2037 (+5,9) | |||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 6/2025 | 5/2033 (+6,1) | ||||
4 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 11/2027 | 6/2034 (+7,0) | ||||
5 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 5/2030 | 8/2037 (+5,9) | ||||
6 | 7. | 2/2024 | D1 | 13,5 km | 4 | 1 235 mil. € | 13 676 - 21 949 | 1 | 1 | 3/2008 | 12/2030 (+4,5) | ||||
6 úsekov |
111,0 km |
2 - 4 |
3 299 mil. € |
5 762 - 21 949 | 3,0 |
3,0 |
12/2030 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku