dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
|||||||||
1 | 32. - 33. | 12/2026 | D4 | 12,4 km | 4 | 772 mil. € | 3 | 4 | 6/2033 (+3,3) | ||||||
2 | 8. - 9. | 3/2024 | R7 | 9,4 km | 4 | 15 m | 191 mil. € | 6 428 - 9 084 | 4 | 5 | 9/2028 (+3,5) | ||||
3 | 50. - 52. | 5/2030 | R4 | 8,0 km | 2 | 86 m | 133 mil. € | 5 814 - 7 518 | 4 | 3 | 5/2033 (+6,1) | ||||
4 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 433 m | 191 mil. € | 14 233 - 18 874 | 3 | 3 | 6/2034 (+7,0) | ||||
5 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | 295 m | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||
6 | 64. - 68. | 8/2033 | D1 | 15,5 km | 4 | 303 m | 136 mil. € | 1 698 - 6 812 | 4 | 3 | 8/2036 (+7,7) | ||||
6 úsekov |
108,3 km |
2 - 4 |
1 132 m |
2 085 mil. € |
1 698 - 18 874 | 3,7 |
3,7 |
9/2028 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku