dátum |
plánovaný
|
odhad NDS
|
<3,5 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||||
1 | 5. | 4/2023 | R1 | 8,1 km | 4 | 173 mil. € | 12 387 - 17 316 | 775 - 1 059 | 2 | 3 | 4/2010 | |||||
2 | 7. | 2/2024 | D1 | 13,5 km | 4 | 1 235 mil. € | 13 676 - 21 949 | 869 - 1 422 | 1 | 1 | ||||||
3 | 11. | 6/2024 | R1 | 2,7 km | 4 | 155 mil. € | 16 268 | 893 | 4 | 3 | 4/2010 | |||||
4 | 30. | 10/2026 | R1 | 4,6 km | 4 | 100 mil. € | 11 611 | 623 | 4 | 3 | 4/2010 | |||||
5 | 37. - 38. | 2/2028 | R1 | 14,9 km | 4 | 785 mil. € | 8 140 - 13 204 | 575 - 1 052 | 3 | 3 | 4/2010 | |||||
6 | 55. - 56. | 5/2031 | R1 | 11,5 km | 4 | 406 mil. € | 7 784 | 537 | 4 | 4 | 4/2010 | |||||
7 | 57. - 58. | 6/2031 | R3 | 14,0 km | 4 | 191 mil. € | 14 233 - 18 874 | 911 - 1 315 | 3 | 3 | 9/2010 | |||||
8 | 71. - 78. | po 2040 | R1 | 42,1 km | 4 | 631 mil. € | 5 713 - 13 545 | 469 - 796 | 5 | 5 | ||||||
8 úsekov |
111,5 km |
4 |
3 675 mil. € |
5 713 - 21 949 | 3,3 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku