dátum |
plánovaný
|
odhad NDS
|
>12 t
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 5. | 4/2023 | ![]() | R1 | 8,1 km | 4 | 173 mil. € | 4,4 mil. € | 12 387 - 17 316 | 434 - 541 | 2 | 3 | 12/2019 | ||||
2 | 20. - 23. | 10/2025 | ![]() | R3 | 4,9 km | 2 | 77 mil. € | 2,0 mil. € | 2 | 2 | 1/2023 | ||||||
3 | 53. - 54. | 7/2030 | ![]() | R6 | 11,2 km | 2 | 182 mil. € | 4,8 mil. € | 7 234 | 394 | 4 | 3 | 2/2028 | ||||
4 | 53. - 54. | 7/2030 | ![]() | R6 | 11,3 km | 2 | 222 mil. € | 6,0 mil. € | 2 561 - 5 054 | 292 - 307 | 4 | 3 | 2/2028 | ||||
5 | 57. - 58. | 6/2031 | ![]() | R8 | 54,9 km | 4 | 1 020 mil. € | 28,3 mil. € | 4 151 - 11 477 | 150 - 839 | 3 | 5 | 6/2027 | ||||
6 | 60. - 61. | 8/2031 | ![]() | R3 | 8,7 km | 2 | 94 mil. € | 2,2 mil. € | 7 211 | 562 | 4 | 2 | 1/2029 | ||||
7 | 60. - 61. | 8/2031 | ![]() | R3 | 10,9 km | 2 | 129 mil. € | 3,4 mil. € | 5 586 - 10 745 | 410 - 1 220 | 3 | 2 | 1/2029 | ||||
8 | 62. - 63. | 10/2032 | ![]() | D2 | 6,9 km | 6 | 107 mil. € | 2,9 mil. € | 5 | 5 | 1/2030 | ||||||
8 úsekov |
116,8 km |
2 - 6 |
2 003 mil. € |
54,1 mil. € |
2 561 - 17 316 | 3,4 |
3,1 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku