plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
+ posun v rokoch
za posledné cca 4 roky |
||||||||||
21 úsekov |
275,3 km |
2 - 4 |
7 920 m |
6 189 m |
4 022 mil. € |
3 782 - 50 895 | 3,2 |
3,5 |
7/2021 - 8/2037 | |||||
1 | R2 | 6,2 km | 2 | 0 m | 68 m | 105 mil. € | 5 304 | 2 | 2 | 3/2026 (+4,7) | ||||
2 | R2 | 9,6 km | 2 | 0 m | 449 m | 112 mil. € | 8 634 - 11 116 | 2 | 4 | 3/2031 (+5,9) | ||||
3 | R2 | 9,8 km | 2 | 0 m | 93 mil. € | 6 452 - 10 032 | 5 | 5 | 9/2032 (+5,6) | |||||
4 | R2 | 7,8 km | 2 | 0 m | 73 mil. € | 5 587 | 5 | 4 | 2/2031 (+4,1) | |||||
5 | R2 | 6,8 km | 4 | 0 m | 1 169 m | 171 mil. € | 11 764 - 50 895 | 3 | 3 | 7/2026 (+4,3) | ||||
6 | R2 | 9,1 km | 4 | 0 m | 212 m | 267 mil. € | 8 780 - 11 203 | 3 | 4 | 2024 (+2,8) | ||||
7 | R2 | 6,1 km | 4 | 0 m | 178 m | 143 mil. € | 12 157 | 3 | 4 | 12/2028 (+4,3) | ||||
8 | R2 | 20,7 km | 2 | 0 m | 886 m | 211 mil. € | 6 969 - 10 726 | 4 | 4 | 4/2028 (+4,8) | ||||
9 | R2 | 16,0 km | 4 | 510 m | 496 m | 277 mil. € | 9 654 - 12 079 | 2 | 2 | 10/2028 (+3,2) | ||||
10 | R2 | 18,0 km | 2 | 0 m | 1 015 m | 224 mil. € | 10 140 - 11 010 | 3 | 5 | 12/2029 (+2,8) | ||||
11 | R2 | 13,5 km | 4 | 0 m | 142 mil. € | 9 007 - 9 998 | 2 | 2 | 2021 (+1,1) | |||||
12 | R2 | 49,0 km | 2 | 1 150 m | 295 m | 662 mil. € | 5 762 - 14 648 | 4 | 4 | 8/2037 (+5,9) | ||||
13 | R2 | 10,6 km | 2 | 0 m | 253 m | 125 mil. € | 6 412 - 8 112 | 4 | 4 | 8/2028 (+5,1) | ||||
14 | R2 | 11,5 km | 2 | 593 m | 214 m | 235 mil. € | 7 793 | 2 | 4 | 9/2031 (+5,4) | ||||
15 | R2 | 14,1 km | 2 | 4 282 m | 60 m | 272 mil. € | 5 792 - 7 064 | 3 | 2 | 12/2029 (+5,4) | ||||
16 | R4 | 6,0 km | 2 | 0 m | 199 m | 101 mil. € | 3 782 - 6 302 | 4 | 3 | 5/2033 (+6,1) | ||||
17 | R2 | 18,0 km | 2 | 1 385 m | 226 m | 176 mil. € | 5 189 - 6 389 | 5 | 5 | 2/2032 (+4,9) | ||||
18 | R2 | 2,7 km | 4 | 0 m | 61 m | 59 mil. € | 12 862 | 3 | 4 | 10/2028 (+4,2) | ||||
19 | R2 | 14,0 km | 2 | 0 m | 123 m | 117 mil. € | 5 809 - 8 826 | 5 | 4 | 7/2032 (+5,3) | ||||
20 | R2 | 8,3 km | 2 | 0 m | 57 m | 169 mil. € | 5 277 - 6 250 | 2 | 2 | 8/2026 (+5,1) | ||||
21 | R2 | 17,5 km | 4 | 0 m | 228 m | 287 mil. € | 12 819 - 29 988 | 2 | 2 | 7/2034 (+10,0) | ||||
21 úsekov |
275,3 km |
2 - 4 |
7 920 m |
6 189 m |
4 022 mil. € |
3 782 - 50 895 | 3,2 |
3,5 |
7/2021 - 8/2037 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku