dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | ||||||||
280,1 km |
2 - 4 |
4 229 mil. € |
3,1 |
3,5 |
|||||||||
1 | 69. - 70. | 8/2034 | R2 | 49,0 km | 2 | R 24,5/120(100), plánované v 1/2-profile | Prievidza, Brusno, Handlová, Nová Lehota | 662 mil. € | 4 | 4 | |||
2 | 25. | 1/2026 | D3 | 10,8 km | 4 | D 24,5/80 (100) | Krásno nad Kysucou | 309 mil. € | 2 | 4 | |||
3 | 59. | 7/2031 | R2 | 17,5 km | 4 | R 24,5/100 | Rákoš, Zvolenská Slatina | 287 mil. € | 2 | 2 | |||
4 | 20. - 23. | 10/2025 | R2 | 16,0 km | 4 | R 24,5/120(100) | Trenčianske Mitice | 277 mil. € | 2 | 2 | |||
5 | 16. - 17. | 12/2024 | R2 | 14,1 km | 2 | R 24,5/120, plánované v 1/2-profile | Rožňava, Jablonov nad Turňou | 272 mil. € | 3 | 2 | |||
6 | 3/2020 | R2 | 9,1 km | 4 | DSP spracovaná na R 17,5/100, vyhlásená súťaž na zhotoviteľa stavby na R 24,5/100 | Kriváň | 267 mil. € | 3 | 4 | ||||
7 | 41. | 9/2028 | R2 | 11,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 235 mil. € | 2 | 4 | ||||
8 | 32. - 33. | 12/2026 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Moldava nad Bodvou, Šaca | 224 mil. € | 3 | 5 | |||
9 | 26. | 4/2026 | R2 | 20,7 km | 2 | R 24,5/120, plánované v 1/2-profile | 211 mil. € | 4 | 4 | ||||
10 | 44. - 45. | 2/2029 | R2 | 18,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Plešivec | 176 mil. € | 5 | 5 | |||
11 | 6. | 7/2023 | R2 | 6,8 km | 4 | R 24,5/100 | Ludvíkov Dvor, Haniska | 171 mil. € | 3 | 3 | |||
12 | 13. | 8/2024 | R2 | 8,3 km | 2 | R 22,5/100, plánované v 1/2-profile | Zacharovce, Bátka | 169 mil. € | 2 | 2 | |||
13 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | Trenčín juh, Trenčianska Turná | 143 mil. € | 3 | 4 | |||
14 | 8/2019 | R2 | 13,5 km | 4 | R 24,5/100 | Mýtna | 142 mil. € | 2 | 2 | ||||
15 | 28. - 29. | 8/2026 | R2 | 10,6 km | 2 | R 22,5/100, plánované v 1/2-profile | Rimavská Sobota | 125 mil. € | 4 | 4 | |||
16 | 47. | 7/2029 | R2 | 14,0 km | 2 | R 24,5/120, plánované v 1/2-profile | Turňa nad Bodvou | 117 mil. € | 5 | 4 | |||
17 | 39. - 40. | 3/2028 | R2 | 9,6 km | 2 | R 24,5/120(100), plánované v 1/2-profile | Nováky - západ | 112 mil. € | 2 | 4 | |||
18 | 8. - 9. | 3/2024 | R2 | 6,2 km | 2 | R 22,5/100, plánované v 1/2-profile | 105 mil. € | 2 | 2 | ||||
19 | 48. - 49. | 9/2029 | R2 | 9,8 km | 2 | R 24,5/120, plánované v 1/2-profile | 93 mil. € | 5 | 5 | ||||
20 | 37. - 38. | 2/2028 | R2 | 7,8 km | 2 | R 24,5/120, plánované v 1/2-profile | Jablonov n.Turňou | 73 mil. € | 5 | 4 | |||
21 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 3 | 4 | ||||
280,1 km |
2 - 4 |
4 229 mil. € |
3,1 |
3,5 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku