dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 7/2016 | R7 | 17,4 km | 4 | R 24,5/120 | 8 544 - 13 236 | 2 | 3 | 7/2020 (0,0) | |||||||
2 | 7/2016 | R7 | 8,4 km | 4 | R 31,5/120 | 13 102 - 19 993 | 1 | 1 | 7/2020 (0,0) | |||||||
3 | 12. | 7/2024 | R3 | 6,5 km | 2 | R 24,5/120, plánované v 1/2-profile | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 0,10 | |||||
4 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R 24,5/80, plánované v 1/2-profile | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 0,94 | |||||
5 | 24. | 12/2025 | R2 | 6,1 km | 4 | R 24,5/120(100) | 143 mil. € | 12 157 | 3 | 4 | 0,10 | |||||
6 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R 24,5/120(100) | 59 mil. € | 12 862 | 3 | 4 | 0,65 | |||||
7 | 6/2014 | D1 | 13,5 km | 4 | D 26,5/100 | 555 mil. € | 22 691 - 32 334 | 1 | 2 | |||||||
7 úsekov |
62,9 km |
2 - 4 |
1 026 mil. € |
5 550 - 32 334 | 2,0 |
2,7 |
7/2020 |
0.1 - 0.94 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku