dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané | |||||||||||
1 | 12. | 7/2024 | R3 | 6,5 km | 2 | privádzač Krupina | 70 mil. € | 6 706 - 9 733 | 123 - 165 | 2 | 2 | |||||
2 | 16. - 17. | 12/2024 | R7 | 8,4 km | 4 | Mliečany s II/507, Dolný Bar | 161 mil. € | 6 403 - 9 478 | 32 - 113 | 4 | 5 | |||||
3 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | Dlhá nad Oravou | 77 mil. € | 2 | 2 | |||||||
4 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | Podbiel | 199 mil. € | 5 550 - 9 787 | 88 - 175 | 2 | 3 | |||||
5 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | 1 | 59 mil. € | 12 862 | 115 | 3 | 4 | |||||
6 | 24. | 12/2025 | R2 | 6,1 km | 4 | Trenčín juh, Trenčianska Turná | 143 mil. € | 12 157 | 35 | 3 | 4 | |||||
7 | 71. - 78. | po 2040 | R3 | 58,5 km | 2 | Budča, privádzače D. Niva, Babiná, Hont. Nemce, Dudince, Semerovce | 3 | 611 mil. € | 3 247 - 11 434 | 45 - 182 | 4 | 4 | ||||
95,4 km |
2 - 4 |
4 |
1 320 mil. € |
3 247 - 12 862 | 2,9 |
3,4 |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku