dátum |
plánovaný
|
odhad NDS
|
1 - veľmi vysoká,
5 - veľmi nízka |
1 - optimálne,
5 - neprimerané |
prebratie
| ||||||||||||
1 | 12. | 7/2024 | R3 | 6,5 km | 2 | R3 juh | 70 mil. € | 6 706 - 9 733 | 2 | 2 | 5/2015 | 12/2023 | 47. | |||||
2 | 20. - 23. | 10/2025 | R3 | 4,9 km | 2 | R3 sever (Orava) | 77 mil. € | 2 | 2 | 2/2016 | 2/2025 | 16. | ||||||
3 | 20. - 23. | 10/2025 | R3 | 8,3 km | 2 | R3 sever (Orava) | 199 mil. € | 5 550 - 9 787 | 2 | 3 | 2/2016 | 2/2025 | 17. | |||||
4 | 20. - 23. | 10/2025 | R2 | 2,7 km | 4 | R2 západ | 59 mil. € | 12 862 | 3 | 4 | 9/2014 | 2/2025 | 23. | |||||
5 | 24. | 12/2025 | R2 | 6,1 km | 4 | R2 západ | 143 mil. € | 12 157 | 3 | 4 | 9/2014 | 4/2025 | 48. | |||||
6 | 71. - 78. | po 2040 | R3 | 10,3 km | 2 | R3 stred (Turiec) | 92 mil. € | 5 098 - 5 557 | 4 | 2 | 2/2016 | 7. | ||||||
6 úsekov |
38,7 km |
2 - 4 |
639 mil. € |
5 098 - 12 862 | 2,7 |
2,8 |
12/2023 - po 2040 |
7. - 48. |
jednotlivé fázy: 1 - Technická štúdia, 2 - EIA - Správa o hodnotení, 3 - EIA - Záverečné stanovisko, 4 - Štúdia realizovateľnosti (prebratie), 5 - Dokumentácia na územné rozhodnutie, 6 - Územné rozhodnutie, 7 - Dokumentácia na stavebné povolenie, 8 - MPV pre stavebné povolenie - zmluvy k pozemkom, 9 - Stavebné povolenie - predpoklad NDS, 10 - Dokumentácia na ponuku